Barnes County’s draft hog farm permit remains open for comment after hearing

North Dakota is taking comments through Dec. 4 on the Blackhawk Farms proposal for up to 8,461 hogs near Valley City.

Archive photo from 2009 showing the Barnes County Courthouse in Valley City, where the Nov. 19 hearing took place. · Andrew Filer, CC BY-SA 2.0
Archive photo from 2009 showing the Barnes County Courthouse in Valley City, where the Nov. 19 hearing took place. · Andrew Filer, CC BY-SA 2.0

Barnes County residents have until Dec. 4 to weigh in on a proposed hog operation about 14 miles north and seven miles east of Valley City. North Dakota’s Department of Environmental Quality heard from residents and supporters at the Barnes County Courthouse on Nov. 19. The state is still taking comments on the Blackhawk Farms proposal, which would house up to 8,461 hogs. Hearing notice · Deadline extension

Valley News Live reported that neighbors raised concerns about water availability, pollution and road safety. A representative of the North Dakota Soybean Growers Association argued that the project would benefit nearby farmers. The station also reported that the state hearing officer said the department would respond to comments after the deadline and then decide whether to issue or deny the permit.

What the draft would require

The draft state permit, NDAFO0916, would require daily inspections of water lines and weekly checks of stormwater diversion equipment and liquid levels in manure storage. It would also require the operator to follow a nutrient management plan when spreading manure and keep field-level application records for at least five years.

One detail matters for people near fields where manure could be spread. The draft requires application practices that prevent manure from washing into state waters. In the same clause, it recommends incorporating manure into the soil within eight hours when applied within half a mile of an occupied residence, building or public area where people may be present. Residents who want that timing made mandatory can identify condition 5 and ask the department to address it.

The state’s public notices page lists the Dec. 4 deadline. The original notice, in Appendix A of the permit fact sheet, gives the submission details and still shows the earlier Nov. 30 deadline. The department says comments and information submitted become part of the public record.