A data center waiting for a transmission upgrade could get some power sooner under a proposal California ISO filed on November 16. The trade would be written into an agreement before the site is energized: it could connect while work is still underway, but it would have to cut its draw when specified grid conditions call for it.
The proposed tariff defines a large load as an end user at a single site with a peak demand of at least 50 megawatts and one or more connections to the grid California ISO controls. That is a test of peak demand at the site, so adding a second connection does not by itself put a project outside the definition. The proposal generally excludes sites already operating or with a complete request on file with the participating transmission owner before February 16, 2027. A later modification or expansion that qualifies under the transmission owner's tariff, or a decision to opt in, can bring a site under the new rules.
Under the interim option, California ISO, the transmission owner and the customer or its representative would sign an agreement setting the operating limits, what triggers a cutback, who carries it out, how fast they must respond and which upgrades or facilities will end the restrictions. California ISO says it would post those agreements publicly. For anyone tracking a proposed data center, that agreement would answer a question a project's advertised megawatt figure cannot: how much power the site can actually take from the grid while it waits for the work to finish.
California ISO asked federal regulators to make most of the changes effective February 16, 2027. That is a proposed start for the rules, not a date when any particular data center would get power. The filing describes a switch to firm service after the necessary upgrades are complete and leaves a permanent flexible option for future work.