GAO asks ICE to update detention spending plan and price future expansion

The plan ICE gave auditors in July projected more than $38 billion in fiscal 2026 commitments from the 2025 detention appropriation. ICE reported about $10 billion in obligations as of fiscal year-end.

Inside the Social Circle, Georgia, warehouse that federal auditors identified as one ICE planned to sell. · U.S. Government Accountability Office, GAO-27-108665, Figure 2
Inside the Social Circle, Georgia, warehouse that federal auditors identified as one ICE planned to sell. · U.S. Government Accountability Office, GAO-27-108665, Figure 2

U.S. Immigration and Customs Enforcement still projected more than $38 billion in fiscal 2026 commitments from its long-term detention funding in a plan it provided to auditors in July. ICE reported about $10 billion in obligations from that funding as of fiscal year-end. The Government Accountability Office’s November 19 report compares the amount ICE expected to commit with the amount it actually obligated. An obligation is a commitment to pay, which can precede a cash payment.

The figures concern detention funding from the 2025 reconciliation law, which provided $45 billion available through fiscal 2029. ICE bought 11 warehouses for about $1.07 billion before scaling back its plan to convert warehouses into detention space. It planned to sell seven. ICE also bought four existing detention facilities in July and August 2026 for about $2.2 billion in total. GAO said the scope, schedule and estimated costs of further purchases remained undetermined.

An updated spending plan would show when ICE expects to commit funds and which projects it expects to fund. GAO found that the version it reviewed presented annual estimates for two accounts without project descriptions or a schedule for commitments. The auditors also said that committing the remaining funds by the end of fiscal 2027, as the plan indicated, could leave limited funding for maintenance and operations through fiscal 2029. GAO’s spending-plan findings

A life-cycle estimate answers a different question. It puts the upfront cost of a project alongside the bills it generates over time, including operation and maintenance. That gives ICE a basis for comparing options such as buying or leasing space. GAO recommended that ICE and the Department of Homeland Security develop those estimates and evaluate alternatives before significant new investments. GAO’s acquisition findings and recommendations

DHS agreed with both recommendations and asked GAO to close the spending-plan recommendation, saying ICE had developed, approved and updated its plans in line with agency guidance. DHS also said ICE had an approved fiscal 2027 plan for those funds. GAO kept the recommendation open and said ICE still needed to show that the fiscal 2027 plan had more realistic assumptions and supporting details. DHS said ICE would work with the department on a standard process for estimating long-term costs and comparing alternatives. DHS response and GAO evaluation