How Pacific Power’s Oregon data center rates charge for power held in reserve

A new rate schedule separates the cost of keeping power available from the cost of using it. An empty server hall can still leave a bill.

AI-generated illustration. An empty bay beside installed server racks represents power capacity held in reserve. · United Herald
AI-generated illustration. An empty bay beside installed server racks represents power capacity held in reserve. · United Herald

A data center can leave part of a server hall empty and still owe Pacific Power for the capacity it asked the utility to keep ready. That is one consequence of the November 13 order in which Oregon utility regulators approved a settlement setting the terms for a new electricity rate schedule for qualifying facilities in Pacific Power’s Oregon service area. The commission directed the utility to file new tariff sheets by November 24 for a January 1, 2027, effective date.

The order’s eligibility rules start with facilities that use or can use at least 20 megawatts and primarily provide computing infrastructure, data processing, web hosting or related services. An older power contract does not automatically exempt a facility. The settlement also covers some facilities with contracts signed before June 16, 2025, if qualifying investments after that date could expose other customers to higher costs or risks.

Under the standard reservation charge, a customer that contracts for 50 megawatts but peaks at 30 in a given month still has a reservation charge based on 50. The 30-megawatt peak figures in a separate demand charge, and the hourly energy charge is tied to market prices at an approved point on the grid. The numbers are an example, not a customer’s bill. The agreement also provides a different charging structure when the customer specifies which power resources will serve it.

The settlement generally makes the facility pay upfront for network upgrades needed to serve it. An exception applies to certain shared transmission upgrades: the facility pays an assigned share instead. If the customer defaults and its payments and collateral fall short, Pacific Power can ask regulators in a future rate case to recover the remaining costs of that shared upgrade from other customers. The utility has to show, among other things, that keeping the upgrade in service benefits its Oregon customers more than removing or selling it.

For households, the decision sets rules for assigning costs; it does not put a dollar figure on what anyone will save. It also leaves a separate tariff filing for large facilities outside Schedule 401. For now, the UE 463 docket is where customers can find the order and track the tariff filings.