A solar contract could cover most of a data center’s electricity use over a year and still leave it short at night. Spain’s cabinet approved a rule Friday that makes those two questions separate for large data centers connecting to the grid. Royal Decree 1032/2026 was published Saturday and took effect Sunday, Nov. 22. The cabinet’s account confirms the Friday approval.
The power requirements generally apply to projects with at least 10 megawatts of grid access capacity, including facilities under the same ownership at one location that reach that threshold together. Projects with permits in hand can still be covered if they had yet to connect when the decree took effect. In that situation, the general rule gives developers six months to document compliance with the power requirements or their permits expire. Scope and transitional provision five
Articles 7 and 8 set two targets. The first requires eligible renewable supply to cover 80% of total electricity use, through qualifying self-consumption or long-term renewable power contracts. The second generally requires at least 80% of what the facility uses in each hour to be backed by renewable electricity generated in that same hour. Storage can count toward hourly matching under the decree’s rules. A hypothetical site using 10 megawatt-hours in one hour needs 8 megawatt-hours of eligible backing for that hour under the standard rule. If it has 6, it is 2 short even if it clears the overall test.
The first transitional provision gives qualifying facilities a five-year phase-in measured from the decree’s effective date. Through 2028, the requirement is 60% in each hour in the P1 grid tariff period. From January 2029 through the end of the phase-in, it rises to 70% in P1 and adds 60% in P2. A site taking that route must enter service before Dec. 31, 2030, qualify for Spain’s automatic load reduction system, and be able to cut its grid draw to zero within the time the system operator specifies.
The trade-off shows up in two different records. To check hourly matching, the system operator compares the facility’s electricity use with output from the renewable and storage assets linked to it. To get the slower rollout, the facility must also pass tests that qualify it to respond to the system operator’s signal. A power contract addresses supply. The additional test asks what the facility can do when the grid needs it to use less. Article 8 and transitional provision one