Missoula County starts work on data center rules while permit pause stays in place

The zoning study sets up a rule rewrite after Montana’s 2027 legislative session. The existing pause has a July 8 deadline, and power costs are before a separate regulator.

AI-generated illustration. A building sketch and an electrical cable represent separate decisions on zoning and power costs. · United Herald
AI-generated illustration. A building sketch and an electrical cable represent separate decisions on zoning and power costs. · United Herald

A developer seeking a permit for a new or expanded data center outside Missoula city limits still faces the same pause as before Thursday’s hearing. On November 12, Missoula County commissioners approved a study and told staff to start work on new zoning rules. The vote did not adopt those rules or extend the pause.

The county stopped permitting new or expanded data centers in July, with the pause scheduled to run through July 8, 2027, unless new zoning replaces it sooner. Staff are to finish the new rules after the 2027 Montana legislative session so they can account for any changes in state law. Those are two separate clocks: Montana’s interim zoning law allows a single one-year extension, and commissioners must hold a separately noticed public hearing before the pause expires if they want to extend it.

The county’s instructions to staff also separate what can be addressed through local zoning from what requires work with state lawmakers or other agencies. The county identifies noise and vibration as potential local impacts. For residents concerned that a large new power user might leave other customers paying for infrastructure it no longer needs, the commissioners directed staff to stay involved in the Montana Public Service Commission’s proceeding on NorthWestern Energy’s proposed rules for large new electricity users.

Under NorthWestern’s proposal as described in its quarterly filing, the utility would use a standard process for customers who buy both electricity and delivery from NorthWestern. The state commission’s notice puts the threshold for new or expanded service at an average monthly demand of 5 megawatts. At an average monthly demand of 50 megawatts or more, a signed service agreement would go to state regulators for approval before service began. The governor’s office summary of the proposal lists minimum service commitments, collateral and termination costs among the proposed protections. A county zoning decision can determine what gets permitted at a site; it does not set those power contract terms. For a nearby resident, the county’s next notices are the place to look for changes to the permit pause, while the state utility case is where to look for who would bear the cost of serving a large new customer.